PROJECT MANAGEMENT FORM · ARTIFACT 8 OF 8

Project Charter

PROJECT · TWO BATCHES A DAYNORTHGATE BILLING GROUPCHARTER DATE · TUESDAY, OCTOBER 20, 2026ONE PAGE

Two Batches a Day — submitting in smaller, earlier batches

A ONE-PAGE AGREEMENT, SIGNED BEFORE WORK BEGINS

Purpose

Northgate Billing Group submits claims in one large batch a day, so an error made in the morning is usually found the next day — after it has had time to repeat. This project moves the team to two smaller batches a day (noon and 3:30 p.m.), so errors are caught the same day they are made, rework falls, and the gauge rises from its charter baseline of 73.5% toward 80.0% — with no added hours and no change to what counts as a verified claim.

Scope

In scope

  • Submission timing and batch size for all clinic queues
  • The pre-submit checklist, updated for the two-batch rhythm
  • The WIP board’s submission-prep limits, if the pilot calls for it
  • A two-week pilot on two queues, then a team-wide rollout if Gate 3 passes

Out of scope

  • Any change to the gauge’s definition — that belongs to the Register, not this project
  • Staffing levels, hours, and pay
  • Clinic contracts and payer agreements
  • New software or a new billing system

Milestones

DateMilestoneOwner
Fri Oct 23, 2026Pilot designed and Gate 2 passedElena — submissions
Mon Oct 26 – Fri Nov 6, 2026Pilot runs: two batches a day on two clinic queuesElena — submissions
Fri Nov 20, 2026Pilot results independently verified; Gate 3 decidedJune — verification
Fri Dec 4, 2026If Gate 3 passes: two-batch standard work written, posted, and briefedMarcus — coding review
Fri Dec 11, 2026Closing review: gauge read against the 80.0% aim; project closed or extended in writingDana — team lead

Roles

  • Dana — team lead: project lead; owns the plan, the gates schedule, and the closing review.
  • Elena — submissions: owns the pilot design and the daily two-batch runs.
  • June — verification: verifies pilot results independently; keeps the gauge register.
  • Marcus — coding review: writes the standard work if the pilot passes.
  • Priya — charge entry: readies morning charges for the noon batch; reports entry-side effects of the pilot.
  • Tom — denial follow-up: watches denial volume during the pilot and reports any change weekly.
  • Alex — clinic services manager (sponsor): agrees the clinics’ information cutoff with clinic contacts; signs this charter with the team lead.

Measures of success

  • Gauge: from 73.5% (week of October 12–16, 2026) toward 80.0% by December 11, 2026, read under the register’s current definition throughout.
  • Rolled throughput yield: from 80.0% toward 86.0% over the same period.
  • Flow time: average batch flow time at or below the current 2.0 days throughout the pilot — speed bought by batching smaller, never by skipping verification.
  • No harm: near-misses logged do not fall during the project — reporting stays honest while the numbers improve.

Sign-off

Dana*

Dana — team lead, project lead
Signed Tuesday, October 20, 2026

Alex*

Alex — clinic services manager, sponsor
Signed Tuesday, October 20, 2026

June*

June — verification, register keeper
Signed Tuesday, October 20, 2026